|
|
CH2M HILL OMI Seattle
Cedar Water Treatment Facility (Water Infrastructure)
2006 NCPPP Infrastructure
Award Winner
Project Location: Seattle, WA
Public Sector Partner: Seattle Public Utilities
Contact Name: Chuck Clarke, 206.684.5851
Private Sector Partner: CH2M
HILL OMI
Contact Name: Jim West, 425.255.7238,
jwest1@omiinc.com

|
| Project
Summary:
|
Seattle Public Utilities
(SPU) is one of only a few major metropolitan water utilities
in the United States that doesn't filter all its water. While
the city obtains a majority of its water supply from a pristine,
90,500 acre watershed, changing water regulations required
SPUto consider either installing a $200 million filtration
system or looking into alternatives to filtering their water.

Historically, SPU's water was treated only with chlorine,
corrosion control chemicals, and fluoride. Having faced a
similar challenge in the past, SPU turned to a design-build-operate
(DBO) approach to help them manage the water treatment for
the Cedar River Watershed water.
Thanks to a partnership with CH2M HILL and
its operations and maintenance business unit, CH2M HILL OMI,
Seattle-area residents now receive even higher quality drinking
water that has been treated with state-of-the-art ozonation
and ultraviolet (UV) treatment. The new Cedar Water Treatment
Facility is among the first - and is the largest facility
in the U.S. - to combine the technologies to treat drinking
water, ensuring that SPU's customers continue to receive high-quality
water for the best price. The new facility provides enhanced
treatment that exceeds current and future water quality standards
and improves taste and odor. CH2M HILL's contracted scope
included design, permitting, material and equipment procurement,
construction, onsite inspection, start-up, commissioning,
and operations (for up to 25 years) of the facility.
As the first water treatment plant in the
nation to employ UV technology on a large scale, the facility
treats 180 mgd (million gallons of water per day). The UV
and ozone treatments, combined with watershed protection,
eliminate intensive chemical use and costly filtration. CH2M
HILL OMI will operate the facility for 15 years with the option
to extend the contract up to an additional 10 years. As Seattle's
needs grow, the facility is expandable to 275 mgd.
|
| Originality: |
As the first water treatment
plant in the nation to employ UV technology on a large scale,
Seattle Public Utilities' Cedar Water Treatment facility treats
180 million gallons of water per day. The ultra violet (UV)
and ozone treatments, combined with watershed protection, eliminate
intensive chemical use and costly filtration. CH2M HILL OMI
will operate the facility for 15 years with the option to extend
the contract up to an additional 10 years. As Seattle's needs
grow, the facility is expandable to 275 mgd.
The automated plant operates with less staff,
yet reliably provides 70 percent of Seattle's drinking water.
With the innovative design-build-operate (DBO) process, the
CH2M HILL family of companies will save the city about $50
million over the estimated cost of a conventional design-bid-build-city-operate
procurement.
CH2M HILL's design of the Cedar Water
Treatment Facility was based on "least impact" to
the pristine environment of the Lake Youngs Reservation. Impacts
to wetlands were avoided by using a dispersed site layout,
minimizing building footprints, reusing existing infrastructure,
and upgrading wetland habitat through native plantings. Approximately
85 percent of the waste generated during construction was
recycled. In January 2006 the CH2M HILL designed and constructed
operations building earned the LEED Gold certification. LEED
is a building rating system developed by the U.S. Green Building
Council.
|
| Quality: |
CH2M HILL was responsible for ensuring that
the Cedar Water Treatment Facility met high industry standards
and addressed Seattle Public Utilities' (SPU) and its own
quality objectives
through all stages of development, permitting, construction,
testing, startup, and operation. Quality in every phase of
the Cedar Water Treatment Facility project was essential in
the decision to allow SPU to build this new drinking water
plant using a DBO delivery process. State and federal regulatory
agencies had to be assured that the water flowing into the
community's homes and businesses would be unquestionably healthy,
comply with current and anticipated drinking water regulations,
and minimize adverse impacts on surrounding sensitive areas,
including wetlands.
A comprehensive quality program was
developed for the project, with an independent quality manager
assigned to oversee all quality activities. Since CH2M HILL
OMI's operations began, we have met 100% of state and federal
requirements and 99.7% of SPU's even more stringent water
quality standards.
|
| Implementation: |
The team defined outcomes of minimum environmental
impact, permitability, water quality performance, and constructability,
then integrated design and construction to achieve the outcomes.
CH2M HILL designed a 400-foot-long intake system to draw water
from Lake Youngs at various depths up to 50 feet to optimize
raw water quality and minimize treatment costs. To minimize
impact on the reservoir's potable water during construction,
the designers and constructors created an innovative design
that allowed most of the intake fabrication to take place
on shore. Minimizing the project footprint, beyond conventional
siting methods, became an integral part of the design. To
achieve the tightest footprint, the design re-used as many
existing facilities as possible, and also incorporated many
vertical features. For instance, normally ozone treatment
requires large covered concrete structures for contact time.
The innovative design converted two existing 78-inch-diameter,
2,500-foot-long pipelines into the ozone contact system. This
reduced environmental impact, streamlined permitting, and
cut project costs. CH2M HILL also partnered with the UV vendors
to design the first vertical equipment configuration.
|
| Economics: |
CH2M HILL designed, secured all
permits, constructed, and is now operating the 180-mgd facility.
These services were contracted for approximately $50 million
less than previously estimated by SPU, had a conventional design-bid-build
procurement process been used. In addition to the cost savings,
the schedule for constructing the Cedar Water Treatment Facility
was considerably shortened, thus providing high-quality water
to Seattle residents in record time and lessening the construction
impact on nearby residences. |
| Public-Private
Partnership : |
The City chose the DBO process as a way to
encourage designers, contractors, and operators
to work together for successful project delivery. As a result,
SPU has saved millions of dollars, considerably reduced the
schedule for constructing their new facilities, and greatly
reduced the impact on the environment and nearby residences.
"I'm very proud of our Cedar Treatment Facility. It saved
millions of dollars for Seattle ratepayers and provides state-of-the-art
water treatment that meets new and emerging water quality standards
and assures high quality and reliable water for future generations,"
said Chuck Clarke, Director of Seattle Public Utilities. |
|
|